CM ANNOUNCEMENTS MONITORING SYSTEM – Public Works (B&R) Deptt. of Provincial Division, Narnaul
For the month ending 30/06/2010
Sr. No.
Distt. Anc. Code
Anc. Code
Date of Anc. Place
Constituency
Block
District
Announcement in Brief Estimate cost
Admn. Approved
(Rs. in lacs)
Expdt. upto date Likely date of initiation Likely date of completion Status Pending/
In progress /
Commissioned/
Not Feasible
Present Position /
Completion schedule
1
6
872
20/05/2005 Kanina
Jatusana
Kanina
Mohindergarh
Construction of road from Kakrala to Mandola. 212.69
FC&PS 9/258/05-3B&R(W)
dated 13.12.05
92.23 2007-08 31.5.2010 Completed Work completed.
2
14
982
07/05/2006 Mohindergarh
Mohindergarh
Mohindergarh
Mohindergarh
Constn. of Railway Over Bridge on Riwasa Railway Phatak. 1600.00
FC PW No. 6/13/200-2 B&R (W)
Dt. 18-2-06
1387.76 2007-08 31.8.2010 In progress. All structural work completed. Service road completed except widening portion which yet to be decided. Mastic concrete & painting / finishing is in progress.
3
18
986
07/05/2006 Mohindergarh
Mohindergarh
Mohindergarh
Mohindergarh
Const. of Bye-pass road at Mohindergarh. 1500.00
No
No
No
-- -- -- Pending This project most probably be taken under the World Bank Scheme from Kotputli to Bhiwani road for Upgradation by providing four lanning and the proposed bye-pass shall be constructed against this scheme.
4
19
987
07/05/2006 Mohindergarh
Mohindergarh
Mohindergarh
Mohindergarh
Four lane road Jatwas to Riwasa. (CRF-Scheme) 342.67
NH12037 / 175 / 2002 / HR / NH1
1-Aug-2007
255.68 2007-08 30.06.09 Completed. Work completed.
4
19
987
07/05/2006 Mohindergarh
Mohindergarh
Mohindergarh
Mohindergarh
Four lane road from Rao Tula Ram Chowk upto C.S.D. Canteen. 77.49
9/215/2006-3B&R(w)
30-Jul-2007
106.17 2007-08 30.6.09 Completed. Work completed.
5
20
988
07/05/2006 Mohindergarh
Mohindergarh
Mohindergarh
Mohindergarh
Const. of New Road Satnali to Nangal Mala via Degrota. 219.98
FC&PS 9/291/06-3 B&R(w) dt. 14.2.2007
138.15 2007-08 31.7.09 Completed. Work completed.
1
12
980
07/05/2006 Mohindergarh
Mohindergarh
Mohindergarh
Mohindergarh
Constn. of S.D.O. Civil Complex (Administrative Block) at Mohindergarh. 383.09
FCR No. 4337-R6-2006/13955
Dated 30-11-06
364.20 2006-07 31.7.2010 In progress Work completed except painting / finishing which is in progress.
6
28
1177
04/06//2006 Narnaul
Narnaul / Ateli.
Mohindergarh
Mohindergarh
Constn. of Narnaul Bye-pass. 2500.00
No
No
No
--- --- --- Pending This project most probably be taken under the World Bank Scheme from Kotputli to Bhiwani road for Upgradation by providing four lanning and the proposed bye-pass shall be constructed against this scheme.
6
11
979
07/05/2006 Mohindergarh
Mohindergarh
Mohindergarh
Mohindergarh
Constn. of 50 bedded hospital at Mohindergarh. 125.74
FC&PS No. 20/111/2006-05-HB-II / 350
Dt. 18.12.06
109.81 2006-07 31.8.2010 In progress Structural work completed except connecting passage with old existing building. 97% work of plastering / flooring of Ground floor completed. 80% plaster work completed in first floor. Tile terracing / flooring / joinery work is in progress.
3
15
983
07/05/2006 Mohindergarh
Mohindergarh
Mohindergarh
Mohindergarh
Constn. of Sport Stadium at Mohindergarh. 63.29
FC&PS Sports endst. No. Sports-Grant-Const-2007/4004-10
dt. 26.4.07
53.91 2007-08 31.8.2010 In progress Work completed except painting / finishing and boundary wall which is in progress.

---
---
---

04/06/2006 Narnaul
Narnaul
Mohindergarh
Mohindergarh
Constn. of building for Govt. College for Education, Narnaul. 271.04
FC&PS 4/70-05 works (2) dt. 18.10.06
234.34 2006-07 31.8.09 Completed. Work completed.
36
33
2488
27/10/2007 Narnaul
Ateli
N. Chaudhary
Mohindergarh
Repair of Nangal Choudhary to Nizampur road. 660.39
FC&PS memo No. 9/112/2008-6(W)
dt. 22.8.08
631.80 2008-09 30.6.09 Completed. Work completed.
3
40
2885
17/2/2008 Ateli
Ateli
Ateli
Mohindergarh
Hospital at Ateli. 760.82
Project Director (RCH-II) SIHFW Sector-6, Panchkula memo No. RCH-2/Budget/2009/ 7201-06
Dt. 13.8.2009
124.56 2009-10 27.2.2011 In progress. Footing and tile beam completed and 75% ground floor slab laid and 25% first floor slab laid and 50% brick work completed in Ground floor and further work in progress.
49
2970
--
17/2/2008 Ateli
Ateli
Ateli
Mohindergarh.
Pucca road from Garhi Ruthal to Mundia Khera if the width is 5 Karam or more than it. --
--
--
--
--- --- --- Pending DPR sent to Govt. vide Engineer-in-Chief, Haryana PWD B&R Branch, Chandigarh memo No. 347 dated 12.9.2008 for Rs. 185.01 lacs. Having a length of 5.90 Km.
50
2971
--
17/2/2008 Ateli
Ateli
Ateli
Mohindergarh.
Construction of various roads in Ateli Constituency.

27.27

--

172.14


4.84


--

--


2009-10


--

2009-10


31.07.10


--

--


In progress.

Pending


Pending

Out of 23 Nos. demands of roads only 2 Nos. roads are feasible as under and 1 No. road desired by Hon’ble PWM.
(i) Road from Karia to Bocharia: - Administrative Approval received vide FC&PS memo No. 9/134/08-B&R dated 23.10.08 for Rs. 27.27 lacs. Metalling completed & further work in progress.
(ii) Garhi Ruthal to Mundia Khera road: - DPR sent to Govt. vide E.I.C. memo No. 347 dt. 12.9.08 for Rs. 185.01 lacs.
(ii) Road from Rewari-Narnaul road to Shahpur Doyam: - Administrative Approval received for Rs. 172.14 lacs vide FC&PS memo No. 9/145/08-3-B&R (w) dated 3.12.2008. LA paper under section-IV stands submitted to L.A.O. Bhiwani for publication.
54
3091
--
6/7/2008 Narnaul
Narnaul
Narnaul
Mohindergarh
Widening of Mohindergarh-Narnaul road from 7.00m to 10.00m 1020.00
MOST memo No. NH-17012 / 2001 / 2008-P&M dt. 5.11.08
No
43.06 2009-10 22.9.2010 In progress. BM 1.12 Km. completed & further work delayed due to non-receipt of sanction for deforestation from Forest Deptt.
26
1175
--
4/6/2006 Nangal Chau.
Nangal Chau.
Nangal Chau.
Mohindergarh
S/R to PHC Nangal Chaudhary. 12.48
Comm. & Secy. Govt. Hr. Health Deptt. No. 20/100/2005-5 HB-III dt. 11.1.2008
18.62 2008-09 30.11.09 Completed Work completed.
27
1176
--
4/6/2006 Narnaul
Narnaul
Narnaul
Mohindergarh
Repair of road in Narnaul City. 48.79
DUD/TA/2006/1438
dt. 21-Mar-2006
47.60 2006-07 15.9.06 Completed S/R of Urban road from Old Court road Chowk to Behrore Chowk via Aggarsain chowk at Narnaul under LADT-U stands already completed with an expenditure of Rs. 47.60 lacs.
1
3487
64
18/1/2009 Bamanwas
Narnaul
Narnaul
Mohindergarh
Bamanwas to Panchnota road. --- --- --- --- Pending R/C Estimate sent to Govt. vide Head Office memo No. 169 dated 26.4.2010 for Rs. 539.36 lacs.
--
35
2490
27/10/2007 Chillro
N. Chaudhary
Narnaul
Mohindergarh
P.H.C. at Chillro (Nizampur) 207.27
Project Director (RCH II), Health Deptt. No. RCH-2/Budget-2008/14017
39.09 2009-10 31.10.2010 In Progress Slab under floor completed. Brick work upto roof level in progress.
1
76
3779
31/01/2010 Bachhod
ATELI
Ateli-Block
Mohindergarh
Construction of road from Bachhod Air Strip to Delhi-Jaipur N.H.8, Via Kunjpura village. --- --- --- --- Pending Rough cost estimate stands submitted to Head Office vide EE, Narnaul memo No. 178 dated 23.2.2010 for Rs. 407.64 lacs.
1
--
3796
19/02/2010 Mokhuta
Nangal Chaudhary
Mohindergarh
Narnaul / Nangal Chaudhary
Construction of road from village Mokhuta to Musnota. --- --- --- --- Pending Rough cost estimate sent to Head Office vide SE, Bhiwani memo No. 699 dated 9.4.2010 for Rs. 37.79 lacs.
Executive Engineer,
Provl. Divn. PWD B&R Br.,
Narnaul.
 